PMBOK Process Quiz

PMBOK Process QuizPMBOK Process Quiz – Test and Hone!

Think you know your PMBOK processes?

Better to find out your weak areas now while you still have plenty of time to fix them before that important PMP Exam!

Take your time, there are no prizes for rushing. Get yourself a sheet of paper to make notes and think through your answers before writing them down…

Ready?

Okay, so now…

Try my simple quiz!

1. Which process uses up most of the budget in a project?

  • Integrating
  • Planning
  • Executing
  • Monitoring and Controlling

2. Which is the knowledge area where requirements are collected?

  • Communication
  • Scope
  • Integration
  • Quality

3. Which of the following is NOT one of the three initiating process outputs?

  • Business Case
  • Stakeholder management strategy
  • Stakeholder register
  • Project Charter

4. Which process group contains the process Administering Procurements?

  • Planning
  • Monitoring and Controlling
  • Initiating
  • Executing

5. Your project team have been assembled, so in which process group will you perform team building?

  • Executing
  • Initiating
  • Planning
  • Monitoring and Controlling

6. One of the following groups is NOT a process group – but which one?

  • Planning
  • Integrating
  • Closing
  • Executing

7. You identify stakeholders in which knowledge area?

  • Integration
  • Scope
  • Human Resources
  • Communication

8. Work in the future distance is planned at a high level on the work breakdown structure (WBS), but work in the near future can be planned in detail at a low level on the WBS. What is this form of progressive elaboration called?

  • Stage Gate Planning
  • Detailed Phase Planning
  • Progressive Planning
  • Rolling Wave Planning

9. The project life cycle is documented in which process group?

  • Planning
  • Initiating
  • Integration
  • Life Cycle Planning

10. The Monitoring and Controlling process group contains an output called Accepted Deliverables which process is this output from?

  • Perform Quality Assurance
  • Verify Scope
  • Control Scope
  • Perform Quality Control

Okay, check out the right answers below:

1. Which process uses up most of the budget in a project?

  • Integrating
  • Planning
  • Executing
  • Monitoring and Controlling

2. Which is the knowledge area where requirements are collected?

  • Communication
  • Scope
  • Integration
  • Quality

3. Which of the following is NOT one of the three initiating process outputs?

  • Business Case
  • Stakeholder management strategy
  • Stakeholder register
  • Project Charter

4. Which process group contains the process Administering Procurements?

  • Planning
  • Monitoring and Controlling
  • Initiating
  • Executing

5. Your project team have been assembled, so in which process group will you perform team building?

  • Executing
  • Initiating
  • Planning
  • Monitoring and Controlling

6. One of the following groups is NOT a process group – but which one?

  • Planning
  • Integrating
  • Closing
  • Executing

7. You identify stakeholders in which knowledge area?

  • Integration
  • Scope
  • Human Resources
  • Communication

 8. Work in the future distance is planned at a high level on the work breakdown structure (WBS), but work in the near future can be planned in detail at a low level on the WBS. What is this form of progressive elaboration called?

  • Stage Gate Planning
  • Detailed Phase Planning
  • Progressive Planning
  • Rolling Wave Planning

9. The project life cycle is documented in which process group?

  • Planning
  • Initiating
  • Integration
  • Life Cycle Planning

10. The Monitoring and Controlling process group contains an output called Accepted Deliverables which process is this output from?

  • Perform Quality Assurance
  • Verify Scope
  • Control Scope
  • Perform Quality Control

So how did you do?

Get then all right? Well Done!

Got a few wrong? Welcome to the human race!

Check out my PMP Masterclass and get them ALL CORRECT next time around!

Learn How To Pass Your PMP Exam At the First Try Click HERE!

PMP Exam

 

__CONFIG_colors_palette__{"active_palette":0,"config":{"colors":{"36c04":{"name":"Main Accent","parent":-1},"3a8fd":{"name":"Accent Light","parent":"36c04","lock":{"saturation":1,"lightness":1}}},"gradients":[]},"palettes":[{"name":"Default","value":{"colors":{"36c04":{"val":"var(--tcb-skin-color-0)"},"3a8fd":{"val":"rgb(240, 240, 240)","hsl_parent_dependency":{"h":201,"l":0.94,"s":0}}},"gradients":[]},"original":{"colors":{"36c04":{"val":"rgb(255, 204, 102)","hsl":{"h":40,"s":1,"l":0.7}},"3a8fd":{"val":"rgb(241, 241, 241)","hsl_parent_dependency":{"h":0,"s":0,"l":0.94}}},"gradients":[]}}]}__CONFIG_colors_palette__

Join our Project Management Masterclasses

Sign up to receive product updates and special offers from our team.